Variances are calculated by subtracting the actual cost from ____

Respuesta :

thert68
thert68 thert68
  • 02-09-2017
Budgeted cost is the answer as by having the budget plan to compare to, the business, government agency, or non-profit organization can make adjustments to its management of costs or future budgets. 
Answer Link

Otras preguntas

What's the term for: unwilling to bend; unyielding
How to find the reference angle of -11pi/3 ?
write a system of equations and solvea class of 195 students went on a field trip. They took 7 vehicles,some cars and some buses. find the number of cars and nu
Choose the more precise measurement in the pair.  A .) 6.7 mi or  B.) 6 mi
What would cause a decrease in the quality of circulating red blood cells
which designer started as a fashion illustrator before focusing on industrial design?
If 2/5 of a number is added to 1/3 of the same number ,the sum is 22. What is the number?
which designer started as a fashion illustrator before focusing on industrial design?
why dog pants during summer use the cocept of evaporation
explain why the motion of a body which is moving with constant speed in a circular path is said to be accelerated ?